Despite numerous weather related challenges, we finally have a structure that you can walk through & take in the impressive views. Views from each floor turned out far better than we had imagined; rooftop terrace has incredible views as does the master bedroom. The framing on building D is almost 100% complete. We plan to be completed with sheet rocking in a month. These units should be ready to move in October 2019.
Building B has the retaining wall & foundation completed so the framing will start next week. We plan to have these units completed & ready for move in February 2020.
The paving for Westport Drive is 90% complete & makes the drive appeal look much better.